COMPLETED PROJECTS
|
|
Project Title |
Client |
Value(RM' Millions) |
Start |
Complete |
97 |
Upgrading Oxidation Pond at Sek 7, Shah Alam, Selangor |
PKNS |
34.857 |
14/09/2001 |
30/06/2005 |
98 |
Construct and completion 267 units Singe Storey Low Cost Terrace Houses Phase 3 in Pantai Sepang Putra, Ladang Teluk Merbau, Mukim Sepang, Selangor |
Vintage Height |
6.900 |
16/09/2003 |
15/12/2005 |
99 |
Construct and Completion of 888 units Low Cost Apartments in Kg Seri Perantau, Pelabuhan Klang – Phase 2 |
PKNS |
66.300 |
16/10/2003 |
17/02/2005 |
100 |
Construct and Completion of 53 units Shop/Office and 2 Electric Tower in Pusat Bandar Baru Bangi |
IKAZ Engineering |
13.637 |
16/09/2003 |
31/07/2005 |
101 |
Construct and Completion of 136 units 2 Storey Terrace Houses, Phase 1B1 in Sek 10, Taman Perindustrian Pulau Indah, Selangor |
Central Spectrum Sdn Bhd |
11.664 |
12/05/2004 |
11/11/2005 |
102 |
Construct and Completion of Water Treatment Plant in Bernam Jaya, Hulu Selangor, Selangor |
PKNS |
6.062 |
19/07/2004 |
18/07/2005 |
103 |
Construct and Completion of 194 units 2 Storey Terrace houses on lot 8865, Mukim Dengkil, Daerah Sepang, Selangor |
Bukit Hitam Development |
16.120 |
23/11/2004 |
22/02/2006 |
|
Total Project Value = RM 1,200.79
million |
|
|
|
ACHIEVEMENTS
|